Project update

Royal Mint:
On Friday January 15, we had final construction approval for the last few screens on the new Visitors Centre at The Royal Mint.

Bae Baglan:
Before the end of last year the design and manufacture had been completed.
We are now in the process of drawing elevations and details for the last of the internal screens ready for architect approval.

Windsor House:
Elevations and details for the final few steel doors have been drawn and issued for architect approval.

New Bridewell:

Drawing on going and we are nearing 40{0a1c16881c6066bf0894975060704e806027e1c582dd394319fe87346603789b} completion, ready for the next construction phase to begin on site.
Phase 1 of install has already commenced and is progressing well.

Wells Cathedral School:
Ongoing, currently out for architect review.

Sketty Flats:
Ongoing, currently out for architect review.